Estimaciones y Presupuesto de Zaphyr Estimates and Budgeting for Zaphyr
La gestión predictiva de costos es rigurosa. En Waterfall debemos construir un presupuesto exacto desde las bases. Este taller pondrá a prueba tu capacidad para diferenciar costos directos e indirectos, estimar desde abajo hacia arriba (Bottom-Up) y construir la Línea Base. Predictive cost management is rigorous. In Waterfall we must build an exact budget from the ground up. This workshop will test your ability to differentiate direct and indirect costs, estimate Bottom-Up, and construct the Baseline.
Identifica si los siguientes gastos generados en la empresa pertenecen directamente al presupuesto del Proyecto Zaphyr, o si son costos indirectos (compartidos por la organización) que deben prorratearse (Overhead).Identify if the following expenses generated in the company belong directly to the Zaphyr Project budget, or if they are indirect costs (shared by the organization) that must be prorated (Overhead).
Reúnanse en equipos de 3 personas. En la vida real, los proyectos se quedan sin dinero porque los PMs novatos olvidan cobrar los costos indirectos en sus actividades. Deberán calcular el costo total de la Fase 1.2 aplicando la carga de overhead, y luego estructurar el proyecto completo. Utilicen papel o Excel. Gather in teams of 3 people. In real life, projects run out of money because novice PMs forget to charge indirect costs to their activities. You must calculate the total cost of Phase 1.2 applying the overhead burden, and then structure the entire project. Use paper or Excel.
| Paquete de Trabajo (WBS)Work Package (WBS) | Recursos Internos / SubcontratadosInternal / Outsourced Resources |
|---|---|
| 1.2.1 Arquitectura DB |
- 2 Senior Devs (80 hrs c/u a $50/hr) [Interno] - 1 Cloud Architect (40 hrs a $80/hr) [Interno] |
| 1.2.2 Dashboard Telemetría |
- 3 UX Designers (60 hrs c/u a $40/hr) [Interno] - 2 Frontend Devs (100 hrs c/u a $45/hr) [Interno] |
| 1.2.3 Módulo Bloqueo Legal | - Costo Fijo (Subcontratado):Fixed Cost (Outsourced): $12,600 |
| CALCULAR TOTAL FASE 1.2:CALCULATE PHASE 1.2 TOTAL: | ? |
Usando su respuesta del Paso A (que ya incluye directos e indirectos), construyan la estructura final asumiendo los siguientes datos: Using your answer from Step A (which already includes direct and indirects), build the final structure assuming the following data:
Objetivo Final: Calcula el "Total de Actividades", la "Línea Base de Costos" y el "Presupuesto Total".Final Goal: Calculate the "Total Activities", the "Cost Baseline", and the "Total Budget".